Another quarter of a billion zlotys from the European Funds for the construction of S1 express road
On 21 July 2025, we have signed a co-financing agreement for the construction of S1 express road – section between Mysłowice (Kosztowy node) and Oświęcim. The investment realised by the General Directorate for National Roads and Motorways received support from the European Funds for Infrastructure, Climate and Environment 2021–2027.
The new S1 road will connect Mysłowice and Bielsko-Biała. The investment was divided into a total of four stages, each of which received support from the European Funds. Together with the agreement signed on 21.07.2025, the amount of funding equals almost PLN 940 million.
- Maybe you would like to read: Construction of the S1 express road between Kosztowy and Bielsko-Biała, section II and III, PHASE II
According to the schedule submitted by the General Directorate for National Roads and Motorways (GDDKiA), the entire investment is to be completed in 2026, and the total cost will amount to over PLN 2.1 billion.
A modern route in the heart of the region
Under the co-financing agreement signed on 21.07.2025, two sections of the S1 express road will be built with a total length of over 12.8 km, including:
- approx. 9.95 km long section from Kosztowy node (Mysłowice) to Bieruń,
- as well as nearly 2.9 km long section from Bieruń (with the node) to Oświęcim.
Moreover, the scope of works includes, among other things:
- creation of new road nodes, including: Kosztowy II, Bieruń,
- construction of nearly 20 engineering structures (viaducts, bridges, flyovers),
- realisation of drainage systems, noise barriers and accompanying infrastructure,
- creation of two Motorway Service Areas, components of a Traffic Management System, as well as environmental protection elements.
Earlier, i.e., in December 2023, we supported the implementation of:
- Section II: Oświęcim node (with the node) – Dankowice, with a length of 15.17 km,
- Section III: Dankowice – Suchy Potok node (with the node), with a length of 11.57 km.
Co-financing, which we also granted from the European Funds for Infrastructure, Climate and Environment, amounted to nearly PLN 684 million.
Benefits for residents and the economy
Realisation of this investment will bring numerous measurable benefits:
- Improvement of road traffic safety – modern road infrastructure with limited number collision points will reduce the number of accidents.
- Relieving the towns from transit traffic – moving heavy transport outside of built-up areas will improve the quality of life of residents, as well as reduce noise pollution and emissions.
- Strengthening the communication cohesion in the region – the new S1 express road is an important link in the Trans-European Transport Network (TEN-T), which will shorten travel times and facilitate travel between Śląskie and Małopolskie Voivodships, as well as to the Czech Republic.
- An impulse for local and regional economy – better access to sales markets and transport infrastructure means greater investment potential and new jobs.
Strategic investment with EU support
The agreement concluded between CEUTP and GDDKiA is another proof of the effective use of the European funds for the benefit of residents and the development of modern transport infrastructure.
Estimated contractual deadlines for work completion*:
- Section I/B: Kosztowy II node (with the node) – Bieruń node (without the node): 4 October 2025.
- Section I/A: Bieruń node (with the node) – Oświęcim node (without the node) together with Bieruń ringway:
- 16 September 2026.
- Section II: Oświęcim node (with the node) – Dankowice: 21 June 2025.
- Section III: Dankowice – Suchy Potok node (with the node): 30 September 2024.
*according to GDDKiA, as of 22.07.2025.
More information: https://s1-myslowice-bielsko.pl/
Photo: press materials of GDDKiA
EFICE
25 June 2026 | EFICE
CEUTP Training for Employees of Provincial Monument Preservation Offices
On June 16–17, 2026, CEUTP experts conducted a training session in Wrocław for employees of the Provincial Offices for the Protection of Historical Monuments, focusing on the principles for implementing a technical assistance project under the European Funds for Infrastructure, Climate, and Environment 2021–2027.
More
25 June 2026 | EFICE
Expert Workshop on Dual-Use Projects and Transportation Resilience, Featuring CEUTP
On June 19, 2026, an expert workshop titled “Dual-Use Projects and Building the Resilience of the Railway System with the Support of European Funds” was held in Warsaw. Among those participating in the event was Sylwia Cieślak-Wilk, deputy director of CEUTP, who presented an institutional perspective on the role of dual-use infrastructure in the EU’s current and future financial frameworks.
More
25 June 2026 | EFICE
Nearly 424.6 mln zł from European Funds for the modernization of the Ujście Nysy barrage
The Center for EU Transport Projects has signed two agreements with the State Water Management Authority “Wody Polskie” regarding the modernization of the Ujście Nysy weir on the Oder River. The projects, with a total value of over 538 mln zł, will receive nearly 424.6 mln zł in funding from the European Funds for Infrastructure, Climate, and Environment 2021–2027 program.
More
25 June 2026 | EFICE
Via Carpatia Under Construction – CEUTP Experts Visit the Construction Site of the S19 Section North of Lublin
Experts from the CEUTP Department of Environmental Protection visited the construction site of a section of the S19 expressway north of Lublin, which is part of the international Via Carpatia route. The site visit provided an opportunity to assess the progress of the work and the challenges associated with the implementation of one of the most important road projects in eastern Poland.
MoreContact us
Plac Europejski 2, 00-844 Warsaw
Monday – Friday,
hours: 8:15 am – 4:15 pm