Construction of the S19 expressway between Rzeszów Południe and Babica with EU funding
The project includes the construction of a 10.27-kilometre new section of the S19 along with a tunnel, the “Babica” interchange, MOPs, engineering facilities, safety systems and pro-environmental solutions. The General Directorate of National Roads and Highways received over PLN 1.49 billion in EU support for its implementation.
The new section is part of the S19 route, which is part of the expanded TEN-T core network. The investment runs through the municipalities of Boguchwała and Czudec, connecting to the existing Rzeszów Południe interchange and ending at the “Babica” interchange. The project is being implemented with the support of the European Funds for Infrastructure, Climate, Environment 2021-2027. The planned completion of construction work (entire scope of the project) is Q3 2029.
Scope of work
The project includes a wide range of design and construction activities, including:
- Construction of a two-lane expressway with two lanes and an emergency lane in each direction,
- Construction of the “Babica” road interchange,
- Implementation of numerous engineering structures, including flyovers, viaducts, tunnel, culverts,
- Construction of MOP Lutoryż I and II,
- A collision-free crossing over the tracks along with the R-2 traffic circle,
- Installation of noise barriers and special protections for bats,
- Construction of a helipad for LPR helicopters,
- Establishment of a Tunnel Management Center with full equipment,
- Construction of animal crossings, rainwater drainage systems and environmental protection infrastructure,
- Construction and reconstruction of road lighting, storm sewers and colliding technical infrastructure,
- Installation of process ducts, traffic organization systems, BRD elements, as well as the Traffic Management System on the road and in the tunnel.
The Rzeszow Południe – Babica section is a continuation of the existing S19 and an integral part of a larger transport route leading to the border crossing in Barwinek.
Project objectives
The implementation of the investment is of key importance for the region and the entire transport network of Poland. The objectives of the project include:
- Increasing mobility and travel comfort by integrating the route into the TEN-T network,
- Improving communication accessibility of the Subcarpathian region, the country and international links,
- Improving the flow of people and goods, increasing the efficiency of road transport and reducing bottlenecks,
- Relieving the burden on existing infrastructure and improving the quality of life for residents by reducing traffic in built-up areas,
- Increasing the level of safety for traffic participants through new technical standards,
- Improving transit traffic flow and reducing travel times,
- Addressing transportation exclusion and providing climate-resilient infrastructure,
- Reducing emissions by optimizing route routing and improving transportation corridor capacity.
Benefits for the region and the country
The investment will bring tangible benefits:
- Faster and safer travel between southern Poland and the national border,
- Development of the local and regional economy through improved transportation accessibility,
- An increase in the investment attractiveness of Podkarpackie,
- Improving the living conditions of residents in adjacent areas,
- Increasing Poland’s importance in European transport corridors,
- Raising infrastructure standards in accordance with TEN-T requirements.
Project data
- Program: European Funds for Infrastructure, Climate, Environment 2021-2027
- Project number FENX.05.03-IP.02-0002/25
- Title Construction of S19 Rzeszów – Barwinek expressway, section Rzeszów Południe – Babica
- Beneficiary: General Directorate of National Roads and Motorways.
- Total cost according to UoD: PLN 3,033,486,089.04
- Eligible cost: PLN 1,756,065,858.81
- EU funding: PLN 1,492,655,979.98
EFICE
27 March 2026 | Rail Transportation
We transferred European Funds for reconstruction of Otwock and Dęblin stations
On March 2, 2026, we signed an agreement with Polskie Koleje Państwowe (Polish State Railways) (PKP S.A.) for funding of the project No. FENX.04.02-IP.02-0005/25 entitled “Construction and reconstruction of selected railroad stations in the Mazovia and Lublin provinces.” The investment received support in the amount of more than PLN 34 million.
More
26 March 2026 | EFICE
Reconstruction of the Jagiellonów Roundabout – an EU investment that will change the center of Bydgoszcz
The Jagiellonów Roundabout – one of the most important intersections in Bydgoszcz – will undergo a comprehensive reconstruction that will significantly improve the comfort and safety of movement in the heart of the city. For the implementation of this investment, we have provided PLN 27.6 million from the European Funds for Infrastructure, Climate, Environment.
More
19 February 2026 | EFICE
EU support for construction and purchase of new specialized rescue units
The Centre for EU Transport Projects has signed a grant agreement for the project “Construction and purchase of new specialised rescue vessels for the SAR Service” (No. FENX.05.07-IP.02-0001/25). The beneficiary of the project is the Maritime Search and Rescue Service.
More
30 January 2026 | EFICE
Intermodal transport – we have the results of the competition no. FENX.05.06-IP.02-001/24
The list of evaluated projects within the framework of the completed competition No. FENX.05.06-IP.02-001/24 under Priority FENX.05 Support for the transport sector from the ERDF, Measure FENX.05.06 Intermodal transport, European Funds for Infrastructure, Climate, Environment 2021-2027 program has been approved by the Managing Authority of the European Funds for Infrastructure, Climate, Environment 2021-2027 program.
MoreContact us
Contact for Beneficiaries
- submitting applications
- questions about the programs
Information points
Contact form and dedicated
contactfor the media and for citizens
information points
Office CUPT
Plac Europejski 2, 00-844 Warszawa
Monday – Friday
hours: 8:15 – 16:15